Project Description: 

This addition to the existing fuel farm includes the installation of new 12” issue and 10” receipt carbon steel piping to two new site-built tanks as well as the re-routing of a third tank’s issue and receipt piping. Other modifications and/or repairs include 47 each – thermal relief valves with associated piping, 36 each – pressure indicators, and other miscellaneous drains and vents on various sections of existing piping.   

1,000 ft Carbon Steel 
Piping
Fuel Farm Modifications & Repairs