Project Description: 

This repair project included multiple repairs on 2 each – 18” transfer lines as well as the installation of three valve stations, each with 2 each – 18” DBB Full Port plug valves. Talon made repairs on over 600 pipe supports, hot tapped the transfer line for drain downs, and relocated 200 LF of each of the two transfer lines. Other work performed on the project included erosion control for excavations, dewatering, demolition of a wood bridge and valve platform, tree trimming and brush removal, and installation of a fire hydrant.  

800 ft Carbon Steel 
Piping
Pipeline Modfications & Repairs
Project Type